Date: 20-Dec-21

This page has been converted from its original source. View the original 2022 & 2023 Work Plan Scoring Compilation w Ranking Summary_FINAL (PDF)


7 New* & Updated Projects listed from West to East

7 New* & Updated Projects listed from West to East
HWS ID Title Category Narrative Link
21001* Expansion of Shipwreck Point NRCA Capital SRP Project
19103.1 Johnson Creek Triple Culverts Replacement Capital SRP Project
09001.2 Little Hoko River Large Wood Restoration Capital SRP Project
10080.3 Lyre River Protection and Restoration Capital SRP Project
11088.2 Ennis Creek Barrier Replacement Capital SRP Project
09027.2 Siebert Creek Ecosystem Protection & Restoration Capital SRP Project
12098.1 Dungeness River Instream Flow Restoration-Storage Capital SRP Project

Return to top


43 Projects Already on the Work Plan (In Rank Order)

43 Projects Already on the Work Plan (In Rank Order)
PRISM ID Title
09092.1 Dungeness River Floodplain Restoration
09055.1 Elwha River Estuary/Nearshore Conservation and Restoration
09030.1 Dungeness River Riparian Habitat Protection
14106 Elwha Acquisition and Restoration Project
16103 Indian Creek Habitat Restoration Project
09029.1 Dungeness River Large Wood Restoration
13102 Little River LWD Project
09032.1 Dungeness Drift Cell Conservation
09031.1 Dungeness River Riparian Restoration
16102 Morse Creek Acquisition & Restoration
09093 North Sequim Bay Drift Cell Conservation Project
13101.1 Lower Hoko Acquisition and Restoration Project
09009.1 Pysht River Salt Marsh Estuary Restoration Project
12096 Acquisition of Priorities identified in the HCP
09091 Dungeness River Instream Flow Restoration-Irrigation Efficiencies
09011 Twin River Acquisition
09013 Lower Salt Creek Restoration and Protection
09086.1 Pysht Floodplain Acquisition and Restoration
11087 Elwha River Revegetation Project
11085.1 Pysht River Watershed Wood Restoration Phase 4 Project
14107 Sequim Bay Shoreline Restoration
09046 Washington Harbor Habitat Protection Project
09039.2 McDonald Creek Barrier Removal and Channel Restoration
09053 Clallam Watertype Inventory and Assessment
19104 Lyre River Habitat Restoration
19105 Upper Cowan Ranch LWD
10079 Lower Morse Creek Feasibility Study
09003 WRIA 19 Riparian Restoration
11090.1 Siebert Creek Large Wood Restoration
11084 Upper Hoko LWD Restoration Project
10078.1 McDonald Creek Large Wood Restoration
09026 Morse Creek Property Acquisition
19102 Hoko Culvert 80001279 Replacement
09015 Salt Creek Final Fish Passage Corrections Project
11094 Chicken Coop Road Culvert Replacement Project
09015.1 Kreaman Creek, Trib. To Salt Creek
09005 Sekiu Mainstem (RM 2-5) LWD Restoration
09021 Valley Creek Restoration Phase 3
19101 Fish Passage Corrections on Joyce-Piedmont Road

Return to top


Projects Listed in Rank Order (7 Additional Projects in Bold)

  • Cap Max Possible Score = 206.96
  • Non-Cap Max Possible Score = 151.80
Projects Listed in Rank Order (7 Additional Projects in Bold)
Rank Project ID Title Category Weighted Mean Score Normalized Score
1 09092.1 Dungeness River Floodplain Restoration Capital 188.27 0.910
2 09055.1 Elwha River Estuary/Nearshore Conservation and Restoration Capital 181.45 0.877
3 09030.1 Dungeness River Riparian Habitat Protection Capital 177.34 0.857
4 14106 Elwha Acquisition and Restoration Project Capital 175.51 0.848
5 16103 Indian Creek Habitat Restoration Project Capital 174.96 0.845
6 09029.1 Dungeness River Large Wood Restoration Capital 174.44 0.843
7 13102 Little River LWD Project Capital 173.07 0.836
8 09032.1 Dungeness Drift Cell Conservation Capital 173.05 0.836
9 09031.1 Dungeness River Riparian Restoration Capital 170.77 0.825
10 16102 Morse Creek Acquisition & Restoration Capital 169.29 0.818
11 09093 North Sequim Bay Drift Cell Conservation Project Capital 168.80 0.816
12 13101.1 Lower Hoko Acquisition and Restoration Project Capital 168.29 0.813
13 09009.1 Pysht River Salt Marsh Estuary Restoration Project Capital 167.66 0.810
14 09016.2 Elwha River ELJ Project Capital 167.52 0.809
15 16104 Elwha Hot Springs Road Restoration Capital 166.08 0.802
16 12096 Acquisition of Priorities identified in the HCP Capital 165.70 0.801
17 09091 Dungeness River Instream Flow Restoration-Irrigation Efficiencies Capital 163.48 0.790
18 09011 Twin River Acquisition Capital 162.15 0.783
19 09013 Lower Salt Creek Restoration and Protection Capital 161.50 0.780
20 09086.1 Pysht Floodplain Acquisition and Restoration Capital 159.95 0.773
21 11087 Elwha River Revegetation Project Capital 158.93 0.768
22 11085.1 Pysht River Watershed Wood Restoration Phase 4 Project Capital 156.98 0.759
23 14107 Sequim Bay Shoreline Restoration Capital 156.73 0.757
26 09053 Clallam Watertype Inventory and Assessment Non- 112.37 0.740
27 10080.3 Lyre River Protection and Restoration Capital Capital 153.03 0.739
28 19104 Lyre River Habitat Restoration Capital 152.94 0.739
29 19105 Upper Cowan Ranch LWD Capital 152.33 0.736
30 10079 Lower Morse Creek Feasibility Study Capital 152.17 0.735
31 12098.1 Dungeness River Instream Flow Restoration-Storage Capital 150.28 0.726
32 09003 WRIA 19 Riparian Restoration Capital 149.78 0.724
33 11090.1 Siebert Creek Large Wood Restoration Capital 149.15 0.721
34 11084 Upper Hoko LWD Restoration Project Capital 148.44 0.717
35 10078.1 McDonald Creek Large Wood Restoration Capital 146.66 0.709
36 11088.2 Ennis Creeek Barrier Replacement Capital 145.01 0.701
37 09001.2 Little Hoko River Large Wood Restoration Capital 142.66 0.689
38 09027.2 Siebert Creek Ecosystem Protection & Restoration Capital 141.93 0.686
39 09026 Morse Creek Property Acquisition Capital 138.29 0.668
40 19102 Hoko Culvert 80001279 Replacement Capital 136.34 0.659
41 19103.1 Johnson Creek Triple Culverts Replacement Capital 136.26 0.658
42 21001 Expansion of Shipwreck Point NRCA Capital 133.63 0.646
43 09015 Salt Creek Final Fish Passage Corrections Project Capital 133.57 0.645
44 11094 Chicken Coop Road Culvert Replacement Project Capital 128.36 0.620
45 09015.1 Kreaman Creek, Trib. To Salt Creek Capital 127.13 0.614
46 09005 Sekiu Mainstem (RM 2-5) LWD Restoration Capital 122.16 0.590
47 09021 Valley Creek Restoration Phase 3 Capital 118.39 0.572
48 19101 Fish Passage Corrections on Joyce-Piedmont Road Capital 115.17 0.556
49 09004 Hoko River/ Hermans Creek – Instream LWD Supplementation Capital 104.81 0.506
50 09018 Elwha River Estuary Restoration Capital 102.19 0.494

Projects ranked 45 & up are eligible to apply for SRFB/PSAR funding

Return to top


2022 & 2023 NOPLE Four Year Workplan Scatterplot

4-Yr Workplan Normalized Scores vs. Rank

Scatterplot of normalized project scores by rank. Scores decline from 0.910 at rank 1 to 0.494 at rank 50, with rank 45 marking the SRFB/PSAR eligibility threshold.
Projects ranked 45 & up are eligible to apply for SRFB/PSAR funding.
Data represented in the scatterplot
Rank Normalized Score
1 0.910
2 0.877
3 0.857
4 0.848
5 0.845
6 0.843
7 0.836
8 0.836
9 0.825
10 0.818
11 0.816
12 0.813
13 0.810
14 0.809
15 0.802
16 0.801
17 0.790
18 0.783
19 0.780
20 0.773
21 0.768
22 0.759
23 0.757
26 0.740
27 0.739
28 0.739
29 0.736
30 0.735
31 0.726
32 0.724
33 0.721
34 0.717
35 0.709
36 0.701
37 0.689
38 0.686
39 0.668
40 0.659
41 0.658
42 0.646
43 0.645
44 0.620
45 0.614
46 0.590
47 0.572
48 0.556
49 0.506
50 0.494

Return to top


Assessment of 7 Additional Work Plan Projects

CoV = Coefficient of Variation (Standard deviation/Mean as %)

Assessment of 7 Additional Work Plan Projects
ID Title Scorer(s) Outside 2 Std Deviations? CoV% Flags for Specific Criteria?
21001* Expansion of Shipwreck Point NRCA 0 Yes (Criteria 5 & 8)
19103.1 Johnson Creek Triple Culverts Replacement 0 Yes (Criteria 5 & 7)
09001.2 Little Hoko River Large Wood Restoration 0 Yes (Criteria 5 & 7)
10080.3 Lyre River Protection and Restoration 0 Yes (Criterion 5)
11088.2 Ennis Creek Barrier Replacement 2 Yes (Criterion 7)
09027.2 Siebert Creek Ecosystem Protection & Restoration 0 Yes (Criteria 5 & 8)
12098.1 Dungeness River Instream Flow Restoration-Storage 1 Yes (Criteria 7, 8 & 12)

Takeaways:

  1. 1 of 7 projects had 2 scorers who scored the project outside 2 standard deviations from the mean.
  2. 1 of 7 projects had 1 scorer who scored the project outside 2 standard deviations from the mean.
  3. 5 of 7 projects had a CoV% >50% for two or more criteria.
  4. Criterion 5: “Addresses an ESA-listed stock” was flagged for 5 projects.
  5. Criterion 7: “Protects high-quality fish habitat” was flagged for 4 projects.
  6. Criterion 8: “Restores formerly productive habitat” was flagged for 3 projects
  7. Criterion 12: “Project Readiness” was flagged for 1 project.

Return to top


Individual Project Scoring

Expansion of Shipwreck Point NRCA (21001)

Date
20-Dec-21
Overall Weighted Score
133.63
Mean of all Scores
3.26
SD of all Scores
0.77
2 X SD of all Scores
1.53
Mean – 2 X
1.73
Mean + 2 X
4.80
NS
No Score Given
CoV
Coefficient of Variation (Standard deviation/Mean as %)
Expansion of Shipwreck Point NRCA – scoring by criterion
ID Criteria for Ranking Score 0 to 5 with 5 being best Mean Score Weight Weighted Mean Score CoV (%)
Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
1 Watershed Priority 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 2.96 13.74 0.0%
2 Addresses limiting factor(s) 2.00 2.50 2.00 3.00 5.00 NS 2.00 3.00 2.00 3.00 5.00 5.00 4.50 3.00 3.00 3.00 2.00 3.13 4.08 12.75 36.3%
3 Addresses stock status and trends 4.00 2.50 2.00 5.00 4.00 NS 1.00 4.00 2.50 2.00 5.00 5.00 3.50 2.00 3.00 3.00 2.00 3.16 2.88 9.09 39.5%
4 Addresses progress toward recovery 1.50 2.00 4.00 4.00 5.00 NS 1.00 4.00 2.00 4.00 5.00 4.50 3.00 2.00 3.00 4.00 2.00 3.19 2.81 8.96 40.5%
5 Addresses an ESA-listed stock 3.00 2.00 2.00 4.00 3.50 NS 1.00 4.00 2.00 0.00 5.00 3.00 2.00 0.50 2.00 3.00 1.00 2.38 3.65 8.67 57.8%
6 Addresses other stocks 4.00 3.00 5.00 3.50 5.00 NS 1.00 4.00 2.00 3.00 5.00 5.00 4.00 0.00 3.00 3.00 1.00 3.22 3.27 10.53 48.5%
7 Protects high-quality fish habitat 3.00 2.00 4.00 5.00 4.50 NS 2.00 4.00 1.00 3.00 5.00 5.00 5.00 0.00 3.00 5.00 3.00 3.41 4.12 14.03 45.9%
8 Restores formerly productive habitat 2.00 2.00 2.00 0.00 3.00 NS 1.50 2.00 1.00 2.00 3.00 3.00 0.00 2.00 0.00 0.00 3.00 1.66 4.04 6.69 68.6%
9 Supports restoration and maintenance of ecosystem functions 3.00 2.00 5.00 3.00 5.00 NS 1.50 4.00 3.50 3.00 5.00 5.00 4.00 4.00 3.00 5.00 4.00 3.75 3.88 14.55 29.6%
10 Spatial Scale of Influence 2.50 2.50 3.50 3.50 4.50 NS 2.00 3.00 1.00 3.00 4.50 3.50 5.00 4.00 3.00 2.00 3.00 3.16 3.62 11.43 33.1%
11 Temporal Scale of Influence 5.00 3.00 5.00 5.00 5.00 NS 5.00 4.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.81 3.23 15.54 11.3%
12 Project Readiness 3.00 2.50 4.50 3.50 2.50 NS 2.00 2.00 1.00 3.00 3.00 5.00 0.00 1.00 4.00 3.00 3.00 2.69 2.85 7.66 48.5%
Expansion of Shipwreck Point NRCA – scorer summary
Measure Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
Mean 3.14 2.55 3.64 3.68 4.30 2.05 3.55 2.30 2.97 4.59 4.47 3.39 2.34 3.05 3.39 2.80
CoV 34.6% 29.6% 35.5% 37.5% 20.2% #DIV/0! 66.4% 24.0% 60.5% 43.9% 16.6% 18.2% 53.7% 75.8% 41.5% 43.5% 45.9%
Outside 2 Standard Deviations? N N N N N N N N N N N N N N N N N

Comments

  • Acquisition and protection of nearshore habitats as migration corridors is critical to the future success of many upland restoration projects throughout the Straits and Puget Sound
  • What a great opportunity to protect mostly intact habitat and expand the only NRCA along the marine shoreline!
  • The narrative lacks a clear stock status and trends, a clear definitive statement of stocks documented that use this estuary. Unclear if the project will restore formerly productive habitat because there is no information on stock trends/status. The projects lacks a clear goal on potential acquisition for the amount being asked. What are your priority parcels? Not quite clear what the end result would be. The narrative indicated that not much restoration was needed but points to turbidity from logging roads, will that turbidity remain or will it go away with acquisition. How will the logging road be restored or will it be decommissioned. I like that the project would expand on existing protected property.
  • Criteria 3: scored 3.5 because it addresses a critical stock (nearshore Chinook) as per the stock status and trends table (which would rank this as a 5), however it addresses this stock in a more presumptive and indirect way, whereas the scoring criteria seems intended for projects that directly address those stock. Criteria 5 based on support of ESA fish use in the nearshore indirectly but with a large anticipated cumulative benefit.
  • I’d like to better understand how the Watershed Priority scores were assigned to the Shipwreck Point, Lyre River, and Siebert Creek projects, and why all qualified as Nearshore. The Shipwreck Point and Lyre River projects seem to include nearshore aspects, but the Siebert Creek project appears to be confined to the stream itself. That being said, it would seem that the assigned Watershed Priority score would better reflect that that appears within the Watershed Priorities tab, or 1.867. By what criteria is the Nearshore Watershed Priority assigned?
  • This looks like a great project, but its fit to salmon restoration and recovery is not strong. Think it would be better suited to other sources of funding.

Return to top

Johnson Creek Triple Culverts Replacement (19103.1)

Date
20-Dec-21
Overall Weighted Score
136.26
Mean of all Scores
3.35
SD of all Scores
0.48
2 X SD of all Scores
0.95
Mean – 2 X
2.39
Mean + 2 X
4.30
NS
No Score Given
CoV
Coefficient of Variation (Standard deviation/Mean as %)
Johnson Creek Triple Culverts Replacement – scoring by criterion
ID Criteria for Ranking Score 0 to 5 with 5 being best Mean Score Weight Weighted Mean Score CoV (%)
Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
1 Watershed Priority 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 2.96 10.35 0.0%
2 Addresses limiting factor(s) 4.00 3.00 5.00 NS 5.00 4.50 3.50 3.00 2.50 5.00 3.00 NS 4.50 4.00 2.00 4.00 4.00 3.80 4.08 15.50 24.8%
3 Addresses stock status and trends 2.50 3.00 4.00 NS 4.00 4.00 4.00 3.00 3.50 5.00 4.00 NS 4.00 4.50 4.00 4.00 4.00 3.83 2.88 11.04 16.1%
4 Addresses progress toward recovery 3.00 3.50 4.00 NS 5.00 4.00 2.00 3.00 4.00 3.00 5.00 NS 3.50 4.00 3.00 5.00 3.50 3.70 2.81 10.40 23.3%
5 Addresses an ESA-listed stock 2.00 0.00 2.00 NS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 NS 0.00 0.00 0.00 0.00 0.00 0.27 3.65 0.97 263.9%
6 Addresses other stocks 4.00 4.00 5.00 NS 5.00 3.50 2.00 3.00 3.50 5.00 5.00 NS 4.00 4.50 3.00 5.00 4.00 4.03 3.27 13.19 22.7%
7 Protects high-quality fish habitat 4.50 3.50 4.00 NS 1.50 0.00 0.50 0.00 2.00 4.50 3.00 NS 0.00 0.00 0.00 0.00 2.00 1.70 4.12 7.00 105.3%
8 Restores formerly productive habitat 3.00 4.00 5.00 NS 3.00 3.50 4.00 3.00 3.00 4.00 4.00 NS 3.50 4.00 2.50 5.00 3.50 3.67 4.04 14.81 19.7%
9 Supports restoration and maintenance of ecosystem functions 4.00 4.50 5.00 NS 3.00 4.00 4.00 3.00 4.00 5.00 4.00 NS 4.50 4.00 2.00 5.00 3.50 3.97 3.88 15.39 21.0%
10 Spatial Scale of Influence 3.00 3.50 3.50 NS 2.50 3.50 3.00 2.00 3.00 4.00 4.00 NS 4.00 3.50 2.50 4.00 3.00 3.27 3.62 11.83 19.1%
11 Temporal Scale of Influence 4.50 4.00 4.50 NS 3.00 4.00 5.00 3.00 4.00 5.00 4.00 NS 5.00 5.00 4.00 5.00 5.00 4.33 3.23 14.00 16.1%
12 Project Readiness 4.00 4.00 5.00 NS 5.00 2.50 4.50 3.00 4.50 5.00 3.50 NS 3.00 4.50 4.50 5.00 4.00 4.13 2.85 11.78 19.6%
Johnson Creek Triple Culverts Replacement – scorer summary
Measure Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
Mean 3.50 3.37 4.21 3.37 3.08 3.00 2.46 3.12 4.08 3.58 3.29 3.46 2.58 3.79 3.33
CoV 22.8% 34.1% 21.8% #DIV/0! 46.5% 49.3% 52.2% 48.6% 38.7% 35.7% 36.1% #DIV/0! 49.5% 48.3% 55.9% 48.9% 38.0%
Outside 2 Standard Deviations? N N N N N N N N N N N N N N N N N

Comments

  • Improved access to wetlands and over wintering habitat will assist in run restoration for years to come. The complexity of the wetland habitat makes it worthwhile to increase salmonid access. As much of the burden as possible should fall on the road construction budget.
  • I think this point has been hammered pretty hard already, but it really seems like the county should be putting up some money to deal with their poorly designed and unsustainable road. Maybe it takes another decade for them to come around to that fact, but I think that is okay. It does seem like the project holds real benefit for salmon though.
  • This project needs to happen and it would be great if the county pitched in on costs. That said getting the creek out of the ditch and establishing better connectivity to upstream habitats are a plus.

Return to top

Little Hoko River Large Wood Restoration (09001.2)

Date
20-Dec-21
Overall Weighted Score
142.66
Mean of all Scores
3.49
SD of all Scores
0.43
2 X SD of all Scores
0.86
Mean – 2 X
2.62
Mean + 2 X
4.35
NS
No Score Given
CoV
Coefficient of Variation (Standard deviation/Mean as %)
Little Hoko River Large Wood Restoration – scoring by criterion
ID Criteria for Ranking Score 0 to 5 with 5 being best Mean Score Weight Weighted Mean Score CoV (%)
Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
1 Watershed Priority 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 3.494 2.96 10.35 0.0%
2 Addresses limiting factor(s) 3.50 3.00 4.00 4.50 5.00 4.00 4.00 3.00 4.00 5.00 4.00 NS 4.00 4.50 4.00 5.00 ns 4.10 4.08 16.73 15.4%
3 Addresses stock status and trends 4.00 3.00 4.00 4.00 4.00 4.00 4.00 3.00 4.00 4.00 4.00 NS 4.00 4.50 4.00 5.00 ns 3.97 2.88 11.42 12.1%
4 Addresses progress toward recovery 3.50 3.00 4.00 3.50 5.00 4.00 2.00 4.00 4.00 4.00 5.00 NS 3.00 4.50 3.00 5.00 ns 3.83 2.81 10.77 22.4%
5 Addresses an ESA-listed stock 3.00 0.00 2.00 0.00 1.50 0.00 0.00 0.00 0.00 0.00 0.00 NS 0.00 0.00 0.00 0.00 ns 0.43 3.65 1.58 217.5%
6 Addresses other stocks 4.00 4.00 5.00 4.00 5.00 3.00 4.00 4.00 4.00 5.00 5.00 NS 4.00 4.50 4.00 5.00 ns 4.30 3.27 14.06 13.8%
7 Protects high-quality fish habitat 3.00 3.00 3.50 0.00 4.00 0.00 0.50 3.00 3.50 5.00 3.00 NS 0.00 1.00 0.00 0.00 ns 1.97 4.12 8.10 90.9%
8 Restores formerly productive habitat 3.00 3.50 4.00 5.00 4.50 3.00 4.00 4.00 5.00 5.00 4.00 NS 3.00 4.00 3.00 4.00 ns 3.93 4.04 15.89 18.5%
9 Supports restoration and maintenance of ecosystem functions 4.50 3.50 4.00 4.50 4.50 4.00 4.50 4.00 5.00 5.00 4.00 NS 4.50 4.00 2.00 5.00 ns 4.20 3.88 16.30 17.9%
10 Spatial Scale of Influence 3.00 3.00 3.00 3.50 4.00 3.50 4.00 3.00 3.50 4.00 4.50 NS 3.50 4.00 3.00 4.00 ns 3.57 3.62 12.91 13.9%
11 Temporal Scale of Influence 4.50 4.00 3.50 5.00 4.00 3.50 5.00 3.00 4.50 4.00 4.00 NS 4.00 5.00 2.50 5.00 ns 4.10 3.23 13.24 18.6%
12 Project Readiness 4.50 3.00 4.00 3.00 5.00 3.00 3.00 4.00 4.50 5.00 4.50 NS 4.00 3.00 4.00 5.00 ns 3.97 2.85 11.31 19.9%
Little Hoko River Large Wood Restoration – scorer summary
Measure Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
Mean 3.67 3.04 3.71 3.37 4.17 2.96 3.21 3.21 3.79 4.12 3.79 3.12 3.54 2.75 3.87
CoV 16.8% 33.9% 19.5% 50.2% 23.6% 48.6% 49.0% 34.8% 34.4% 34.3% 34.9% #DIV/0! 48.8% 43.2% 52.3% 48.6% #DIV/0!
Outside 2 Standard Deviations? N N N N N N N N N N N N N N N N N

Comments

  • This experienced project manager will get the most out of this habitat.
  • I struggle with the 0 I gave for question number 5 regarding addresses an ESA-listed stock. I was unsure how to assign a score for this. Also for temporal scale the way I am understanding is that using larger wood with root wads will see that the project holds out longer than using the smaller wood previously used?

Return to top

Lyre River Protection & Restoration (10080.3)

Date
20-Dec-21
Overall Weighted Score
153.03
Mean of all Scores
3.71
SD of all Scores
0.57
2 X SD of all Scores
1.15
Mean – 2 X
2.56
Mean + 2 X
4.86
NS
No Score Given
CoV
Coefficient of Variation (Standard deviation/Mean as %)
Lyre River Protection & Restoration – scoring by criterion
ID Criteria for Ranking Score 0 to 5 with 5 being best Mean Score Weight Weighted Mean Score CoV (%)
Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
1 Watershed Priority 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 2.96 13.74 0.0%
2 Addresses limiting factor(s) 3.50 3.00 2.00 4.00 5.00 NS 3.50 3.00 2.00 5.00 5.00 5.00 4.00 4.50 4.00 4.00 2.00 3.72 4.08 15.17 29.0%
3 Addresses stock status and trends 3.50 3.00 3.00 5.00 4.00 NS 4.00 3.00 3.50 4.00 4.50 4.50 4.00 4.00 4.00 4.00 2.00 3.75 2.88 10.80 19.5%
4 Addresses progress toward recovery 4.00 3.00 4.00 4.50 5.00 NS 2.50 3.00 2.00 5.00 4.50 4.50 4.00 4.00 4.00 4.00 3.00 3.81 2.81 10.71 22.9%
5 Addresses an ESA-listed stock 3.50 2.00 5.00 3.00 3.50 NS 0.50 0.00 1.00 3.00 2.00 3.00 1.00 0.00 2.50 0.00 1.00 1.94 3.65 7.07 77.6%
6 Addresses other stocks 4.00 4.00 4.00 4.00 5.00 NS 3.00 3.00 3.00 5.00 5.00 5.00 4.00 4.00 4.00 4.00 3.00 4.00 3.27 13.08 18.3%
7 Protects high-quality fish habitat 4.00 3.50 4.00 5.00 4.50 NS 4.00 3.00 2.00 4.00 5.00 5.00 4.50 3.50 5.00 5.00 4.00 4.13 4.12 17.00 20.5%
8 Restores formerly productive habitat 3.00 3.00 3.50 3.50 5.00 NS 3.00 4.00 3.00 5.00 3.00 3.00 0.00 2.50 0.00 5.00 3.00 3.09 4.04 12.50 46.9%
9 Supports restoration and maintenance of ecosystem functions 4.50 3.00 4.00 3.50 5.00 NS 3.00 4.00 2.00 5.00 5.00 5.00 4.50 4.50 4.50 5.00 4.00 4.16 3.88 16.13 21.4%
10 Spatial Scale of Influence 3.50 3.00 3.00 3.00 4.50 NS 3.00 3.00 3.00 4.00 5.00 4.00 3.00 4.00 4.00 4.00 3.50 3.59 3.62 13.01 17.8%
11 Temporal Scale of Influence 5.00 4.00 5.00 5.00 4.50 NS 5.00 4.00 4.50 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.81 3.23 15.54 7.5%
12 Project Readiness 3.00 3.00 4.50 2.50 2.50 NS 1.50 2.00 1.00 5.00 3.00 5.00 1.50 2.00 3.00 4.00 3.00 2.91 2.85 8.28 41.8%
Lyre River Protection & Restoration – scorer summary
Measure Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
Mean 3.84 3.26 3.89 3.97 4.43 3.14 3.05 2.64 4.55 4.30 4.47 3.34 3.55 3.72 4.05 3.18
CoV 16.4% 20.9% 23.0% 22.0% 17.3% #DIV/0! 40.2% 39.1% 45.2% 14.4% 24.1% 16.9% 48.5% 39.8% 37.1% 33.6% 36.2%
Outside 2 Standard Deviations? N N N N N N N N N N N N N N N N N

Comments

  • The Lyre River can and should be a more productive system; channelization is a major problem not easily overcome. Property acquisition is an important first step
  • It’s really hard to score a project where the parcels are completely unknown. I felt forced to err on the side of “they won’t be that great for salmon populations”. I’d like to see this project identify specific parcels they think are beneficial to salmon and have some potential to come on the market.
  • I’d like to better understand how the Watershed Priority scores were assigned to the Shipwreck Point, Lyre River, and Siebert Creek projects, and why all qualified as Nearshore. The Shipwreck Point and Lyre River projects seem to include nearshore aspects, but the Siebert Creek project appears to be confined to the stream itself. That being said, it would seem that the assigned Watershed Priority score would better reflect that that appears within the Watershed Priorities tab, or 1.867. By what criteria is the Nearshore Watershed Priority assigned?
  • Project description makes it unclear what parcels are being targeted so it reads kind of open ended. Its going to be difficult to recover the Lyre unless the channelized mainstem is restored. This is the dominant limiting factor in my opinion. The Lyre is too warm to support bull trout and although the WDF stream catalogue says there are pink salmon, I have never seen one.

Return to top

Ennis Creek Barrier Replacement (11088.2)

Date
20-Dec-21
Overall Weighted Score
145.01
Mean of all Scores
3.52
SD of all Scores
0.45
2 X SD of all Scores
0.90
Mean – 2 X
2.62
Mean + 2 X
4.42
NS
No Score Given
CoV
Coefficient of Variation (Standard deviation/Mean as %)
Ennis Creek Barrier Replacement – scoring by criterion
ID Criteria for Ranking Score 0 to 5 with 5 being best Mean Score Weight Weighted Mean Score CoV (%)
Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
1 Watershed Priority 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.530 2.96 7.49 0.0%
2 Addresses limiting factor(s) 5.00 3.00 4.00 4.00 4.50 4.50 5.00 3.00 3.50 NS 3.00 5.00 4.50 4.00 2.50 5.00 4.00 4.03 4.08 16.45 20.5%
3 Addresses stock status and trends 4.00 3.00 4.00 4.00 4.00 4.00 4.00 4.00 3.50 NS 4.00 5.00 4.00 4.00 2.50 5.00 4.00 3.94 2.88 11.34 15.3%
4 Addresses progress toward recovery 4.00 3.00 3.50 3.00 4.00 4.00 3.50 4.00 3.50 NS 5.00 4.50 4.00 3.00 3.00 5.00 4.00 3.81 2.81 10.71 17.2%
5 Addresses an ESA-listed stock 5.00 3.50 5.00 4.00 3.50 4.50 4.50 4.00 3.00 NS 2.00 5.00 3.00 4.00 3.50 0.00 3.50 3.63 3.65 13.23 35.1%
6 Addresses other stocks 4.50 3.50 4.00 4.00 4.00 3.50 4.50 4.00 3.50 NS 5.00 5.00 4.50 3.00 3.50 5.00 3.50 4.06 3.27 13.28 15.5%
7 Protects high-quality fish habitat 4.00 3.00 4.00 0.00 1.50 0.00 0.50 0.00 2.50 NS 3.00 3.50 0.00 1.00 0.00 0.00 2.00 1.56 4.12 6.44 100.4%
8 Restores formerly productive habitat 3.50 4.00 4.50 3.50 4.00 3.00 4.50 3.50 3.00 NS 4.00 5.00 4.50 4.00 0.00 5.00 4.50 3.78 4.04 15.28 31.3%
9 Supports restoration and maintenance of ecosystem functions 3.50 3.50 4.50 4.00 4.00 2.50 3.00 4.00 3.00 NS 4.00 5.00 4.50 4.00 2.00 5.00 3.50 3.75 3.88 14.55 22.3%
10 Spatial Scale of Influence 3.50 3.50 2.50 3.00 3.00 3.50 2.50 3.00 2.50 NS 3.00 5.00 5.00 4.00 3.00 5.00 3.00 3.44 3.62 12.44 25.4%
11 Temporal Scale of Influence 4.50 4.50 3.50 5.00 3.50 4.50 5.00 4.00 4.50 NS 4.00 5.00 5.00 5.00 4.00 5.00 5.00 4.50 3.23 14.54 12.2%
12 Project Readiness 4.00 4.00 4.00 2.50 2.50 3.50 2.00 2.00 4.00 NS 3.00 4.00 2.00 2.50 3.00 5.00 4.00 3.25 2.85 9.26 28.6%
Ennis Creek Barrier Replacement – scorer summary
Measure Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
Mean 4.00 3.42 3.84 3.29 3.42 3.34 3.46 3.17 3.25 3.54 4.54 3.63 3.42 2.46 3.96 3.63
CoV 17.5% 16.2% 19.4% 38.5% 25.5% 37.9% 40.1% 38.2% 19.0% #DIV/0! 26.5% 17.7% 41.1% 31.0% 51.6% 50.0% 22.8%
Outside 2 Standard Deviations? N N N N N N N N N N N Y N N Y N N

Comments

  • Ennis Creek deserves a chance to return to its once, much more productive self.
  • Indicating the percent passability for the culverts can help in understanding the importance of barrier removal against the removal of the upstream barrier on 101. I found it on the WA State Fish Barrier GIS map (33% passable) but others might not have known of that resource.

Return to top

Siebert Creek Ecosystem Protection & Restoration (09027.2)

Date
20-Dec-21
Overall Weighted Score
141.93
Mean of all Scores
3.45
SD of all Scores
0.58
2 X SD of all Scores
1.16
Mean – 2 X
2.29
Mean + 2 X
4.61
NS
No Score Given
CoV
Coefficient of Variation (Standard deviation/Mean as %)
Siebert Creek Ecosystem Protection & Restoration – scoring by criterion
ID Criteria for Ranking Score 0 to 5 with 5 being best Mean Score Weight Weighted Mean Score CoV (%)
Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
1 Watershed Priority 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 4.639 2.96 13.74 0.0%
2 Addresses limiting factor(s) 2.50 3.00 2.00 3.00 5.00 3.00 3.00 3.00 2.00 3.00 5.00 4.50 3.00 3.00 4.00 4.00 2.00 3.24 4.08 13.20 29.5%
3 Addresses stock status and trends 3.00 3.00 2.00 3.50 4.00 4.50 3.50 3.00 3.00 3.00 4.00 4.50 2.50 2.00 4.00 4.00 2.00 3.26 2.88 9.40 25.5%
4 Addresses progress toward recovery 3.00 2.50 3.50 3.50 4.00 3.50 1.50 3.00 2.50 4.00 5.00 5.00 3.00 2.00 4.00 4.00 3.50 3.38 2.81 9.50 27.9%
5 Addresses an ESA-listed stock 3.00 2.50 5.00 1.50 4.00 4.00 0.00 3.00 2.50 3.00 2.00 4.00 1.00 0.50 4.50 0.00 3.50 2.59 3.65 9.45 60.0%
6 Addresses other stocks 3.00 3.00 3.50 3.50 4.00 3.50 3.00 3.00 2.50 3.00 5.00 5.00 4.00 0.00 4.00 4.00 3.50 3.38 3.27 11.06 32.9%
7 Protects high-quality fish habitat 3.00 3.00 4.50 5.00 5.00 4.50 2.50 3.00 3.00 4.00 4.50 5.00 4.50 3.50 5.00 5.00 4.00 4.06 4.12 16.72 21.7%
8 Restores formerly productive habitat 3.00 2.00 3.00 0.00 3.00 2.50 1.50 1.00 2.00 3.00 4.00 3.00 0.00 2.00 0.00 0.00 3.00 1.94 4.04 7.84 67.5%
9 Supports restoration and maintenance of ecosystem functions 4.00 3.50 4.00 3.00 4.00 3.50 3.00 3.00 3.50 5.00 4.50 4.50 4.50 4.00 4.50 5.00 4.00 3.97 3.88 15.41 16.3%
10 Spatial Scale of Influence 3.00 3.50 2.50 3.50 4.00 4.00 1.00 3.00 2.00 4.00 5.00 4.00 3.00 3.00 4.00 4.00 3.00 3.32 3.62 12.03 28.1%
11 Temporal Scale of Influence 5.00 4.00 4.00 5.00 4.50 4.50 5.00 3.00 4.50 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.68 3.23 15.11 11.9%
12 Project Readiness 4.00 2.50 4.00 2.00 2.50 4.00 3.50 2.00 1.00 5.00 3.00 5.00 1.00 1.00 3.00 4.00 3.00 2.97 2.85 8.47 43.5%
Siebert Creek Ecosystem Protection & Restoration – scorer summary
Measure Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
Mean 3.43 3.09 3.55 3.18 4.05 3.84 2.68 2.89 2.76 3.89 4.30 4.51 3.01 2.55 3.89 3.64 3.43
CoV 22.8% 23.5% 28.2% 46.0% 18.0% 17.3% 54.8% 28.7% 38.2% 22.3% 21.9% 13.4% 54.3% 62.3% 34.5% 48.2% 26.7%
Outside 2 Standard Deviations? N N N N N N N N N N N N N N N N N

Comments

  • This small creek has been surprisingly productive for steelhead and should be protected.
  • The broadness of the proposal didn’t help me to gain a good understanding of how it directly benefits ESA-stocks in the nearshore though there was mention that it could extend to nearshore. The readiness of the project wasn’t mentioned, but I am assuming that as parcels become available and there was landowner willingness, they would be submitted for funding. Are there specific landowners that have expressed interest?
  • When listing stock species the stock status and trends table indicates coho as dep/sta, a more detailed narrative of stocks and status would have been helpful. The narrative refers to other stocks but are not indicated in the stock status and trend table for Siebert creek. Having a definitive statement of known stock status rather than general statements may have resulted in different score. Question 8 ) Restores formerly productive habitat is not indicated in the narrative, there is no information on how productive historically this creek was or potential. Historical data would have been helpful and may have resulted in a different score.
  • Criteria 5-Addresses ESA fish use in the nearshore indirectly
  • I’d like to better understand how the Watershed Priority scores were assigned to the Shipwreck Point, Lyre River, and Siebert Creek projects, and why all qualified as Nearshore. The Shipwreck Point and Lyre River projects seem to include nearshore aspects, but the Siebert Creek project appears to be confined to the stream itself. That being said, it would seem that the assigned Watershed Priority score would better reflect that that appears within the Watershed Priorities tab, or 1.867. By what criteria is the Nearshore Watershed Priority assigned?
  • Parcels were clearly identified in this proposal

Return to top

Dungeness River Instream Flow Restoration- Storage (12098.1)

Date
20-Dec-21
Overall Weighted Score
150.28
Mean of all Scores
3.67
SD of all Scores
0.95
2 X SD of all Scores
1.89
Mean – 2 X
1.78
Mean + 2 X
5.57
NS
No Score Given
CoV
Coefficient of Variation (Standard deviation/Mean as %)
Dungeness River Instream Flow Restoration- Storage – scoring by criterion
ID Criteria for Ranking Score 0 to 5 with 5 being best Mean Score Weight Weighted Mean Score CoV (%)
Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
1 Watershed Priority 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 4.699 2.96 13.92 0.0%
2 Addresses limiting factor(s) 4.00 4.00 4.00 4.50 5.00 3.50 4.00 3.00 2.00 NS 5.00 5.00 5.00 4.00 1.00 5.00 2.00 3.81 4.08 15.56 32.4%
3 Addresses stock status and trends 4.00 3.50 3.50 5.00 5.00 3.50 5.00 4.00 4.00 NS 5.00 5.00 5.00 4.00 1.00 5.00 3.00 4.09 2.88 11.79 26.5%
4 Addresses progress toward recovery 4.00 4.00 4.00 4.50 5.00 3.50 4.00 4.00 2.00 NS 4.50 4.50 5.00 4.00 1.00 5.00 3.00 3.88 2.81 10.89 28.1%
5 Addresses an ESA-listed stock 4.50 4.00 5.00 4.50 5.00 4.00 4.00 4.00 4.00 NS 5.00 5.00 5.00 4.50 2.50 5.00 2.50 4.28 3.65 15.63 19.1%
6 Addresses other stocks 3.50 2.00 4.50 4.50 5.00 3.50 4.00 2.00 1.00 NS 5.00 5.00 5.00 2.00 1.00 5.00 3.00 3.50 3.27 11.45 42.4%
7 Protects high-quality fish habitat 4.00 3.50 5.00 0.00 4.00 0.00 0.50 0.00 0.00 NS 3.00 4.00 4.00 2.50 0.00 0.00 1.00 1.97 4.12 8.11 97.9%
8 Restores formerly productive habitat 4.00 3.50 4.00 3.00 5.00 3.50 3.00 3.00 2.00 NS 5.00 4.00 0.00 2.50 0.00 5.00 1.00 3.03 4.04 12.25 53.0%
9 Supports restoration and maintenance of ecosystem functions 3.50 4.00 5.00 3.00 5.00 4.00 4.50 3.00 0.00 NS 5.00 5.00 4.50 4.50 2.00 5.00 1.00 3.69 3.88 14.31 41.7%
10 Spatial Scale of Influence 4.50 4.50 4.50 4.00 4.00 4.00 3.50 4.00 3.00 NS 5.00 5.00 5.00 4.00 2.00 5.00 4.00 4.13 3.62 14.93 19.5%
11 Temporal Scale of Influence 5.00 4.50 4.00 4.50 5.00 4.00 5.00 4.00 1.00 NS 5.00 5.00 5.00 5.00 3.00 5.00 2.50 4.22 3.23 13.63 27.4%
12 Project Readiness 4.00 2.50 4.50 2.50 4.00 1.00 1.00 2.00 0.50 NS 3.00 5.00 2.50 2.50 3.00 5.00 1.00 2.75 2.85 7.84 52.7%
Dungeness River Instream Flow Restoration- Storage – scorer summary
Measure Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
Mean 4.14 3.72 4.39 3.72 4.72 3.27 3.60 3.14 2.02 4.60 4.77 4.22 3.68 1.77 4.56 2.39
CoV 10.9% 21.5% 11.2% 38.0% 9.4% 41.6% 40.4% 41.4% 79.9% #DIV/0! 16.6% 8.2% 36.0% 27.8% 78.0% 31.5% 51.9%
Outside 2 Standard Deviations? N N N N N N N N N N N N N N Y N N

Comments

  • This is an extremely expensive project that should be funded by multiple sources. I just hope the project is large enough and the water cool enough to have a positive impact in a drought stricken fall.
  • This project will also help the Dungeness River become more resilient to changing hydrology due to the effects of climate change.
  • This is not a salmon restoration project and should not be funded with salmon recovery money.

Return to top


Capital Project – MAXIMUM POSSIBLE SCORE

Date: 17-Dec-21

Overall Weighted Score
206.96
Mean of all Scores
5.00
SD of all Scores
0.00
2 X SD of all Scores
0.00
Mean – 2 X
5.00
Mean + 2 X
5.00
NS
No Score Given
CoV
Coefficient of Variation (Standard deviation/Mean as %)
Capital Project – Maximum Possible Score
ID Criteria for Ranking Score 0 to 5 with 5 being best Mean Score Weight Weighted Mean Score CoV (%)
Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
1 Watershed Priority 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 5.000 2.96 14.81 0.0%
2 Addresses limiting factor(s) 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.08 20.40 0.0%
3 Addresses stock status and trends 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 2.88 14.40 0.0%
4 Addresses progress toward recovery 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 2.81 14.05 0.0%
5 Addresses an ESA-listed stock 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 3.65 18.25 0.0%
6 Addresses other stocks 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 3.27 16.35 0.0%
7 Protects high-quality fish habitat 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.12 20.60 0.0%
8 Restores formerly productive habitat 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 4.04 20.20 0.0%
9 Supports restoration and maintenance of ecosystem functions 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 3.88 19.40 0.0%
10 Spatial Scale of Influence 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 3.62 18.10 0.0%
11 Temporal Scale of Influence 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 3.23 16.15 0.0%
12 Project Readiness 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 2.85 14.25 0.0%
Capital Project – scorer summary at maximum possible score
Measure Scorer 1 Scorer 2 Scorer 3 Scorer 4 Scorer 5 Scorer 6 Scorer 7 Scorer 8 Scorer 9 Scorer 10 Scorer 11 Scorer 12 Scorer 13 Scorer 14 Scorer 15 Scorer 16 Scorer 17
Mean 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
CoV 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Outside 2 Standard Deviations? N N N N N N N N N N N N N N N N N

Return to top


Final Watershed Priorities Sorted by Standardized Score

Date: 17-Dec-21

Final Watershed Priorities Sorted by Standardized Score
WRIA System Overall Standardized Score (Max 5)
18 Elwha River 5.000
18 Dungeness River 4.699
17 + 18 + 19 Nearshore 4.639
18 Morse Creek 4.096
19 Pysht River 3.494
19 Hoko River 3.494
19 Lyre River 3.193
19 Clallam River 2.861
19 Sekiu River 2.831
19 Sail River 2.530
18 Ennis Creek 2.530
19 Salt Creek 2.530
19 Deep Creek 2.199
19 Colville Creek 1.898
17 Jimmycomelately Creek 1.867
19 East Twin River 1.867
19 West Twin River 1.867
18 McDonald Creek 1.867
18 Siebert Creek 1.867
17 Chicken Coop Creek 1.566
17 Dean Creek 1.566
17 Johnson Creek 1.566
19 Butler Creek (19.0112) 1.566
19 Field Creek 1.566
19 Jim Creek 1.566
19 Joe Creek 1.566
19 Murdock Creek 1.566
18 Peabody Creek 1.566
18 Lees Creek 1.566
18 Meadowbrook Creek 1.566
18 Tumwater Creek 1.566
18 Valley Creek 1.566
18 Bell Creek 0.904
18 Cooper Creek (18.0017) 0.904
18 Cassalery Creek 0.904
19 Olsen Creek 0.904
18 Bagley Creek 0.904
18 Dry Creek 0.904
18 Gierin Creek 0.904

Return to top


2022 & 2023 NOPLE Four Year Workplan – Capital Projects Criteria

Date: 17-Dec-21

2022 & 2023 NOPLE Four Year Workplan – Capital Projects Criteria
ID Criteria for Ranking Criteria Narrative 0 1 2 3 4 5 Mean Weight
1 Watershed Priority What is the watershed priority score for this proposal? This criterion is mandated by regulation. The score is calculated based on data concerning historical and current productivity and stock diversity of the NOPLE watersheds. This score is added by Lead Entity staff for the watershed(s) covered by the proposed project. Watershed priority scores have been calculated for each NOPLE watershed. The calculation produced a numerical score based on difference between historical and current watershed productivity plus historical number of stock and stock elements. See separate Watershed Priority Table for data and more details on the calculation. 2.96
2 Addresses limiting factor(s) How well does the proposed work address the limiting factor(s) pertinent to the watershed and stock? Does not mention or address a limiting factor at all Mentions a limiting factor, but addresses only vaguely Indirectly addresses a limiting factor but only minimally Indirectly addresses a limiting factor, but only moderately, OR Directly addresses limiting factor, but only minimally Addresses a limiting factor directly and moderately Addresses a limiting factor directly and substantially 4.08
3 Addresses stock status and trends How well does the proposed work address the status and trends of the stock(s) of interest? Stock fully recovered; no more work needed Addresses recovered stock Addresses rebuilding stock Addresses depressed stock that is increasing Addresses depressed stock that is decreasing Addresses critical stock 2.88
4 Addresses progress toward recovery To what extent does the watershed or nearshore area need further habitat protection and/or restoration efforts? Recovery completed; needs no further efforts to complete recovery Recovery in progress; needs just a little protection and/or restoration effort to complete recovery Recovery in progress; needs some protection and/or restoration effort to complete recovery Recovery in progress; needs moderate protection and/or restoration effort to complete recovery Recovery in progress; needs more than moderate protection and/or restoration effort to complete recovery Recovery in progress; needs substantial or major protection and/or restoration effort to complete recovery 2.81
5 Addresses an ESA- listed stock To what extent does the project benefit listed stocks? Does not mention or address a listed stock at all Mentions listed stock, but addresses only vaguely Indirectly addresses listed stock and only minimally Indirectly addresses listed stock moderately OR Directly addresses listed stock only minimally Directly and moderately addresses listed stock Directly and substantially addresses listed stock 3.65
6 Addresses other stocks To what extent does the project benefit non-listed stocks? Does not mention or address a non-listed stock at all Mentions non-listed stock, but addresses only vaguely Indirectly addresses non-listed stock and only minimally Indirectly addresses non-listed stock moderately OR Directly addresses non-listed stock only minimally Directly and moderately addresses non-listed stock Directly and substantially addresses non-listed stock 3.27
7 Protects high- quality fish habitat How well does the proposed work and instrument protect fish habitat? Does not mention or address criterion at all; benefits not discernible Mentions habitat protections but addresses criterion only vaguely; benefits uncertain at best Addresses criterion only indirectly with only minimal benefits Addresses criterion indirectly with moderate benefits OR addresses criterion directly with only minimal benefits Addresses criterion directly with moderate benefits Addresses criterion directly with substantial benefits 4.12
8 Restores formerly productive habitat How well does the project restore formerly productive habitat? Does not mention or address criterion at all; benefits not discernible Mentions habitat restoration but addresses criterion only vaguely; benefits uncertain at best Addresses criterion only indirectly with only minimal benefits Addresses criterion indirectly with moderate benefits OR addresses criterion directly with only minimal benefits Addresses criterion directly with moderate benefits Addresses criterion directly with substantial benefits 4.04
9 Supports restoration and maintenance of ecosystem functions How well does the project restore and maintain ecosystem functions? Does not mention or address criterion at all; benefits not discernible Mentions ecosystem restoration but addresses criterion only vaguely; benefits uncertain at best Addresses criterion only indirectly with only minimal benefits Addresses criterion indirectly with moderate benefits OR addresses criterion directly with only minimal benefits Addresses criterion directly with moderate benefits Addresses criterion directly with substantial benefits 3.88
10 Spatial Scale of Influence How far does the spatial scale of influence extend through a watershed or nearshore area? Potential spatial scale of influence not mentioned or addressed; scale of benefits not discernible Potential scale of influence minimal; Benefits local (limited to project area) at most and uncertain Potential scale of influence slight; scale of benefits more than local and discernible Potential scale of influence over a moderate portion of a watershed or nearshore area; benefits moderate and spread beyond the project area through part of the system Potential scale of influence over a majority of a watershed or nearshore area; benefits more than moderate and spread through much of the system Potential scale of influence over a watershed or nearshore area; benefits substantial and spread through essentially all of the system 3.62
11 Temporal Scale of Influence How far does the temporal scale of influence extend through a watershed or nearshore area? Potential temporal scale of influence not mentioned or addressed; scale of benefits not discernible Potential scale of influence minimal; Benefits seasonal at most and uncertain Potential scale of influence slight; scale of benefits more than seasonal but less than 1 year and discernible Potential scale of influence of moderate duration; benefits moderate and endure for 2 to 4 years Potential scale of influence of more than moderate duration; benefits moderate and endure for 5 to 10 years Potential scale of influence of long- term to indefinite duration; benefits substantial and endure beyond 10 years 3.23
12 Project Readiness How ready is the project to start now, if funded? Not ready for foreseeable future; Time to overcome known obstacles and fulfill requirements is not determined but not in immediate future Not ready for some years; time to overcome known obstacles and fulfill requirements is greater than 5 years Ready within 3 or 4 years; Remaining obstacles and requirements can be resolved over 3 to 4 years Ready within 2 years; remaining obstacles and requirements can be resolved within 2 years Ready next year; remaining obstacles and requirements can be resolved within 1 year Ready to start now given award of funds; no remaining obstacles or requirements; a ready-to-go project 2.85

Return to top


Capital Projects Criteria Sorted by Mean Weight

Date: 17-Dec-21

Capital Projects Criteria Sorted by Mean Weight
ID Criteria for Ranking Criteria Narrative 0 1 2 3 4 5 Mean Weight
7 Protects high- quality fish habitat How well does the proposed work and instrument protect fish habitat? Does not mention or address criterion at all; benefits not discernible Mentions habitat protections but addresses criterion only vaguely; benefits uncertain at best Addresses criterion only indirectly with only minimal benefits Addresses criterion indirectly with moderate benefits OR addresses criterion directly with only minimal benefits Addresses criterion directly with moderate benefits Addresses criterion directly with substantial benefits 4.12
2 Addresses limiting factor(s) How well does the proposed work address the limiting factor(s) pertinent to the watershed and stock? Does not mention or address a limiting factor at all Mentions a limiting factor, but addresses only vaguely Indirectly addresses a limiting factor but only minimally Indirectly addresses a limiting factor, but only moderately, OR Directly addresses limiting factor, but only minimally Addresses a limiting factor directly and moderately Addresses a limiting factor directly and substantially 4.08
8 Restores formerly productive habitat How well does the project restore formerly productive habitat? Does not mention or address criterion at all; benefits not discernible Mentions habitat restoration but addresses criterion only vaguely; benefits uncertain at best Addresses criterion only indirectly with only minimal benefits Addresses criterion indirectly with moderate benefits OR addresses criterion directly with only minimal benefits Addresses criterion directly with moderate benefits Addresses criterion directly with substantial benefits 4.04
9 Supports restoration and maintenance of ecosystem functions How well does the project restore and maintain ecosystem functions? Does not mention or address criterion at all; benefits not discernible Mentions ecosystem restoration but addresses criterion only vaguely; benefits uncertain at best Addresses criterion only indirectly with only minimal benefits Addresses criterion indirectly with moderate benefits OR addresses criterion directly with only minimal benefits Addresses criterion directly with moderate benefits Addresses criterion directly with substantial benefits 3.88
5 Addresses an ESA- listed stock To what extent does the project benefit listed stocks? Does not mention or address a listed stock at all Mentions listed stock, but addresses only vaguely Indirectly addresses listed stock and only minimally Indirectly addresses listed stock moderately OR Directly addresses listed stock only minimally Directly and moderately addresses listed stock Directly and substantially addresses listed stock 3.65
10 Spatial Scale of Influence How far does the spatial scale of influence extend through a watershed or nearshore area? Potential spatial scale of influence not mentioned or addressed; scale of benefits not discernible Potential scale of influence minimal; Benefits local (limited to project area) at most and uncertain Potential scale of influence slight; scale of benefits more than local and discernible Potential scale of influence over a moderate portion of a watershed or nearshore area; benefits moderate and spread beyond the project area through part of the system Potential scale of influence over a majority of a watershed or nearshore area; benefits more than moderate and spread through much of the system Potential scale of influence over a watershed or nearshore area; benefits substantial and spread through essentially all of the system 3.62
6 Addresses other stocks To what extent does the project benefit non-listed stocks? Does not mention or address a non-listed stock at all Mentions non-listed stock, but addresses only vaguely Indirectly addresses non-listed stock and only minimally Indirectly addresses non-listed stock moderately OR Directly addresses non-listed stock only minimally Directly and moderately addresses non-listed stock Directly and substantially addresses non-listed stock 3.27
11 Temporal Scale of Influence How far does the temporal scale of influence extend through a watershed or nearshore area? Potential temporal scale of influence not mentioned or addressed; scale of benefits not discernible Potential scale of influence minimal; Benefits seasonal at most and uncertain Potential scale of influence slight; scale of benefits more than seasonal but less than 1 year and discernible Potential scale of influence of moderate duration; benefits moderate and endure for 2 to 4 years Potential scale of influence of more than moderate duration; benefits moderate and endure for 5 to 10 years Potential scale of influence of long- term to indefinite duration; benefits substantial and endure beyond 10 years 3.23
1 Watershed Priority What is the watershed priority score for this proposal? This criterion is mandated by regulation. The score is calculated based on data concerning historical and current productivity and stock diversity of the NOPLE watersheds. This score is added by Lead Entity staff for the watershed(s) covered by the proposed project. Watershed priority scores have been calculated for each NOPLE watershed. The calculation produced a numerical score based on difference between historical and current watershed productivity plus historical number of stock and stock elements. See separate Watershed Priority Table for data and more details on the calculation. 2.96
3 Addresses stock status and trends How well does the proposed work address the status and trends of the stock(s) of interest? Stock fully recovered; no more work needed Addresses recovered stock Addresses rebuilding stock Addresses depressed stock that is increasing Addresses depressed stock that is decreasing Addresses critical stock 2.88
12 Project Readiness How ready is the project to start now, if funded? Not ready for foreseeable future; Time to overcome known obstacles and fulfill requirements is not determined but not in immediate future Not ready for some years; time to overcome known obstacles and fulfill requirements is greater than 5 years Ready within 3 or 4 years; Remaining obstacles and requirements can be resolved over 3 to 4 years Ready within 2 years; remaining obstacles and requirements can be resolved within 2 years Ready next year; remaining obstacles and requirements can be resolved within 1 year Ready to start now given award of funds; no remaining obstacles or requirements; a ready-to-go project 2.85
4 Addresses progress toward recovery To what extent does the watershed or nearshore area need further habitat protection and/or restoration efforts? Recovery completed; needs no further efforts to complete recovery Recovery in progress; needs just a little protection and/or restoration effort to complete recovery Recovery in progress; needs some protection and/or restoration effort to complete recovery Recovery in progress; needs moderate protection and/or restoration effort to complete recovery Recovery in progress; needs more than moderate protection and/or restoration effort to complete recovery Recovery in progress; needs substantial or major protection and/or restoration effort to complete recovery 2.81